Project description:

Envelope restoration at the Life Unik project, Yehud: treating concrete segregation and fallen plaster at complex points

Background:
During maintenance inspections at the Life Unik project in Yehud, we found segregation in the concrete and fallen plaster in sensitive, complex areas at height. This created a safety hazard and let water into the building envelope, which called for thorough, precise treatment.

The project’s challenges:

✔ Segregation in the concrete: weakened areas of the envelope where the concrete had not spread evenly, leaving weak pockets exposed to moisture.
✔ Fallen plaster at complex points: especially in hard-to-reach areas, where the work at height had to be done in complex conditions.

The solution:

🔹 Advanced concrete restoration: targeted treatment of the segregation with strengthening materials and rebuilding of the damaged elements.
🔹 Repairing and cleaning the damaged plaster areas: removing loose plaster and restoring the building’s outer protective layer.
🔹 Precise work at height without scaffolding: an efficient solution in places that conventional methods struggle to reach.
🔹 Strengthening and waterproofing the envelope: to prevent future water penetration and keep the building stable.

The result:

✅ The building was strengthened and fully waterproofed
✅ The fallen plaster was fully treated, preventing future risks
✅ The work at height was done quickly and precisely, with no disturbance to the residents’ routine
✅ The building’s outer protective layer was restored and will hold for a long time

Life Unik in Yehud is another example of the importance of early detection, thorough restoration and advanced work-at-height methods in preserving a building’s quality for years.